Forum Discussion
lamccle
Dec 09, 2024Copper Contributor
Gantt Chart not showing properly
Something happened with my Gantt that is is showing off to the side and I cannot see the full Gantt. Please help!
Dec 10, 2024
lamccle --
Drag the split bar to the right edge of the Duration column. Click the View tab (at the top of Microsoft Project) to display the View ribbon. In the Zoom section of the View ribbon, click the Timescale pick list button and select the Days item. Does that help? Let us know.