Forum Discussion
Gantt Chart not showing properly
Iamccle,
If by "off to the side" you mean there is a separation between the tabular data and the Gantt Chart graphic, all you need to do is to place your mouse over the vertical line dividing the two and drag the graphic part back to the left.
However, I notice one other thing about your plan. All performance tasks (i.e. non-summary lines) are manually scheduled. Manual scheduling should only be used during initial development of a plan. Once a plan is complete and ready for execution, all tasks should be auto-scheduled. That allows Project to dynamically schedule the plan. It of course assumes all tasks are linked in a logical sequence of performance.
John
I have done a drag all the way to the left and it still will not show.
Understand about the auto-schedule versus the manual. I will be working on that soon.
- graham25May 13, 2025Copper Contributor
how did you solve this
- John-projectMay 13, 2025Silver Contributor
graham25,
Whereas this post is 6 months old and Iamccle never did give us further feedback, I suggest you create a new post and include a screen shot of your issue. Also tell us what version of Project you are using.
John
- John-projectDec 10, 2024Silver Contributor
Iamccle,
I guess I don't understand what is not showing. On the Gantt Chart view there are two slider at the bottom. One for the tabular data and one for the Gantt graphic. Have you tried using the slider for the graphic data
John