Forum Discussion
thelonestar
Oct 11, 2022Copper Contributor
Gantt Chart not refreshing after changing Bar Style
I am a first time MS project user and have this product as part of Office 365. I was trying to add the Task Name to the left of the Gantt Chart bar against each task. By default, the Gantt chart was ...
- Oct 11, 2022thelonestar --
Since you are a new user of Microsoft Project, I suspect that you are using Manually Scheduled tasks in your project since that is the default Task Mode setting for all new tasks. If this is the case, that would be the cause of your problem, as I think you probably changed the settings for tasks that are NOT Manually Scheduled (these would be called Auto Scheduled tasks).
If I have correctly diagnosed the cause of the problem, the solution would be to change the settings for the Manual Task line item in the Bar Styles dialog. Hope this helps.
thelonestar
Oct 11, 2022Copper Contributor
Yes Dale...that is exactly what the problem was. Thanks a lot. So the only way to assign the Task Name if all my tasks are manually scheduled, would be to individually change it for each bar in the gantt chart, is it ?
Oct 11, 2022
No, if all of your tasks are Manually Scheduled, display the Bar Styles dialog and then change the settings for the Manual Task line item. This will update all of your Manually Scheduled tasks in a single action. No need to do it one task at a time.