Gantt Chart not refreshing after changing Bar Style

I am a first time MS project user and have this product as part of Office 365. I was trying to add the Task Name to the left of the Gantt Chart bar against each task. By default, the Gantt chart was ...
  • Dale_HowardMVP's avatar
    Oct 11, 2022
    thelonestar --

    Since you are a new user of Microsoft Project, I suspect that you are using Manually Scheduled tasks in your project since that is the default Task Mode setting for all new tasks. If this is the case, that would be the cause of your problem, as I think you probably changed the settings for tasks that are NOT Manually Scheduled (these would be called Auto Scheduled tasks).

    If I have correctly diagnosed the cause of the problem, the solution would be to change the settings for the Manual Task line item in the Bar Styles dialog. Hope this helps.