Gantt chart help with late, but active task formatting
I have a master project file, where I have several sub projects linked in and I'm having multiple issues, but one thing at a time. First up, I have Baseline Start and Baseline finish set up to ca...
Dr_Edward_Hanna
Mar 10, 2023Copper Contributor
The green Gantt bar you mention (i.e. Actual Progress) will indeed grow--but you have to tell it "how much to grow" by making entries in the % Complete column for this task. Alternatively, you can use the "Update Project" feature in the ribbon to mark selected tasks (or all tasks) as complete through a specified date. That too will grow your green Progress bars.
Freeboro
Mar 14, 2023Copper Contributor
Ok, so it only moves as you update the % complete. Makes sense.
I don't understand "Update Project". I don't want it to do either of the options it presents, completing or re-scheduling.
I don't understand "Update Project". I don't want it to do either of the options it presents, completing or re-scheduling.