Gantt: Calendar Start

I am trying to get the timescale to begin directly beside the last column in the table. I have changed my project start date to ensure that it is correct. I have also adjusted the timescale several t...
  • John-project's avatar
    May 03, 2023
    EthanSix,
    I don't know of any way to always make the first Gantt bar start right at the beginning of the Gantt display, but here's what you can do. Select the earliest task or summary line and go to, Task > Editing group > Scroll to task. That won't bring the bar over to the vertical divider but it will bring it to a convenient location.

    Hope this helps.
    John