Gantt activity duration
Hi,
I have a simple problem but cant resolve it.
How can i set up my setting so when a activity lasts 2 days (lets say it starts monday), the gantt view shows it ends at the end of tuesday?
I put 2 days for duration but it shows 2.5 days in my gantt!
I´m just gonna use the gantt view to see full days, not hours
Thank you guys!
Renzo
- John-projectSilver Contributor
Renzo,
Sorry but you don't give quite enough information. What exactly are you trying to do? A screen shot might help, especially the part where you say you entered 2 days duration but the Gantt bar shows 2.5 days. That just doesn't compute.
What is your project calendar?
What is your definition of a "day" in Project options?
What are the timescale tier settings?Also, keep in mind that Project keeps track of time to the nearest minute, regardless of what unit is selected for duration.
John- RenzobbCopper Contributor
Thanks John for the response. Sorry for the poor information, I understand that there are many configurations in project and I have only recently started using it. Attached you will find a screenshot of what i mean. The activity duration is 1.56 days and in the gantt view it marks three days.
I think this happened because i started to change the calendar settings and the working hours.
My settings where:
- Calendar: Standard
- Start hour: 0:30
- End hour: 23:30
- Hours per day: 24
I started a new Project sheet and started from 0, every configuration as default and i didn't have a problem.
Thanks for your time and help, have a wonderful week!
Regards,
Renzo
- PlannersPlaceBrass Contributor
Your calendar setting from 00:30 to 23:30 shows you have 23 hrs in a day not 24 hrs. So, when you enter 2 days (48 hrs), this shows up on Gantt over 2+ days, 23 hrs on 1st day, 23 hrs on 2nd day & 2hrs on 3rd day.
Either change your hours per day to 23 hrs or change your start time from 00:00 to 00:00.
=jerome