Forum Discussion
Molalenge
Oct 25, 2024Brass Contributor
GANNT CHART
My Gannt Chart suddenly disappeared while I was updating resource information. I can see it under "Tracking Gannt," but not the Gannt Chart! How do I recover my data? Thanks
- Oct 25, 2024
John-project
Oct 25, 2024Silver Contributor
Molalenge,
Sounds like the Gantt Chart view got corrupted. Try this. Note: your will lose any custom formatting you had on the Gantt Chart view.
1. Select any view other than the Gantt Chart
2. Go to File > Info > Organzie Global Template
3. Select the Gantt Chart view in the selection list on the right side
4. Hit the "Delete" button, then "Yes", then "Close"
Now select the Gantt Chart view. Is it working?
John
Molalenge
Oct 25, 2024Brass Contributor
- John-projectOct 25, 2024Silver ContributorMolalenge,
You're welcome and thanks for the feedback. If I answered your question, please consider marking my response as the answer.
John