Forum Discussion

quinn87's avatar
quinn87
Copper Contributor
Mar 10, 2021
Solved

Formula for custom field

Hi Community,  I am trying to create a formula to graphically represent my project's status but it's not going so well. Here is what i would like to formula to represent:   If task is 100% complet...
  • John-project's avatar
    John-project
    Mar 12, 2021

    quinn87 

    Thanks for posting your formula. Here are my comments/suggestions.

     

    First, you mention Status Date but your formula uses Current Date. They are different. I suspect you do mean the current date but if not, you need to change the formula appropriately. If you do change to the Status Date, make sure you have actually set a status date or the formula will give an error, testing for "NA" takes special consideration.

     

    Second, the criteria for 14 days works okay the way you have implemented it as long as you mean 14 calendar days. However, if you really mean 14 working days, then you need to use the ProjDateDiff function and be sure to add an extra day (i.e. 480 minutes) if you want the difference to be inclusive (i.e. current date "through" the 14th working day). Without the extra day, the result will be "up to" the 14th day.

     

    Third, your formula shows a result of "1" as the default but you don't say what color that is. I might assume it would be the same of for unstarted tasks (i.e. white) but maybe not.

     

    Fourth, I'd move the test for tasks that don't start until after the current date as the second test in the formula. As currently structured a task with a start date within the 14 day window will show as amber, not white, but, tasks with a start date beyond the 14 day window will show a white.

     

    Assuming you do want tests based on the current date and you do want 14 calendar days, this is how I'd write the formula:

    IIf([% Complete]=100,4,(IIf([Current Date]<[Start],6,(IIf([Current Date]>=[Finish],3,(IIf([Current Date]>[Start] And [% Complete]=0,5,(IIf([Current Date]>[Finish]-14 And [% Complete]<80,2,1)))))))))

    John