For a resource engagement, is there a unique identifier assigned to each resource engagement?
hi there. we are trying to find if there is a unique identifier/number to each resource engagement that is created in Project desktop. does anyone know if there is a unique identifier to each re...
- Jun 29, 2023
We don't use that functionality, but if you look at the Project Server data definition for the Engagements table there is an EngagementUID that identifies each engagement.
https://learn.microsoft.com/en-us/projectonline/project-online-and-project-server-export-data-definitions#Engagements
RodFromm
Jun 29, 2023Steel Contributor
We don't use that functionality, but if you look at the Project Server data definition for the Engagements table there is an EngagementUID that identifies each engagement.
https://learn.microsoft.com/en-us/projectonline/project-online-and-project-server-export-data-definitions#Engagements