Flow shop flexible simulation

I'm learning microsoft project 2016 , because I think I will need it for my career, I learned how to put a new project with tasks and resources etc.... now I'm wondering if I can put a flow shop flexible production system with 3 machines in ms project to calculate the duration of project and all the resources needed etc..???

1 Reply

  • as for any project you need to work out what the tasks are, how they relate to each other and their duration / effort / resource. When you have set up the logical network of tasks and their durations you have the shortest the project could be. Then you look at resource conflicts and work out what has to be delayed to allow all resources to be properly utilised. Then you have a schedule.