Flag for increase/decrease structure level is not working
Hi, I'm trying to click on flag for opening or hiding my level of structure but it not working. Is there any option is forcing this option? Thank you very much.
John-project
Apr 08, 2022Silver Contributor
Dariocg,
I vaguely remember an issue like yours but I can't recall the reason.
1. Is your file a single file (i.e. not part of a linked structure like a master/subproject or resource pool/sharer)?
2. Is a filter applied?
A screen shot might help.
John
I vaguely remember an issue like yours but I can't recall the reason.
1. Is your file a single file (i.e. not part of a linked structure like a master/subproject or resource pool/sharer)?
2. Is a filter applied?
A screen shot might help.
John
Dariocg
Apr 11, 2022Copper Contributor
Thank you John,
it is a subproject. I have opened it now and it is woking correctly...
it is a subproject. I have opened it now and it is woking correctly...
- John-projectApr 11, 2022Silver ContributorDariocg,
You're welcome and thanks for the feedback.
John