Forum Discussion

Ed_Ooms's avatar
Ed_Ooms
Copper Contributor
Mar 14, 2022
Solved

Fixed duration task / Effort Driven: Why is the 3rd resource set at 50% by Project?

I just don't see why Project would assign the 3rd resource as 50%? I use Project 2019 but it's the same in Project 2013. Standard file, no edits in Kalenders or so. Work and Peak values are fin...
  • John-project's avatar
    John-project
    Mar 15, 2022

    Ed_Ooms 

    This "phenomenon" occurs when effort driven is checked (default) for a fixed duration task. The effort driven strives to keep the work content constant and you can see that in the Task Usage view as you assign each of the 3 resources consecutively.

     

    Here's the interesting part. Instead of 3 resources, consecutively assign 4 resources at 100% to the task. As each resources is assigned you will see the Assignment Units replicate the previous resource's units while the Peak adjusts to maintain the constant work value. So for the second assignment, the assignment units is still 100% but the Peak reduces to 50%. Then when the third resource is assigned, the assignment units takes on the peak unit value from the first two assignments (i.e. 50%) and the peak now readjusts to be equal for all 3 assignments (i.e. 33%). If you assign a fourth resource, the assignment units takes on the previous peak (i.e. 33%) and the peak now readjusts to spread the original work content over 4 resources so it shows 25%.

    Is this a good enough explanation for your "students"? Don't know, but it might make their heads spin a bit 🙂

     

    I do recall there was a change to the way peak units are calculated, circa Project 2010 or Project 2013 (I think), but I don't remember the details. Whether that has anything to do with this issue, I don't know.

    John