Finish Variance - Deadline Date Settings

Understanding that when you assign a deadline to a task, that if the scheduled finish is later than the deadline, MSP calculates the total slack for that task and its predecessors as the difference b...
  • Miles_Goodchild's avatar
    Miles_Goodchild
    May 24, 2021
    Maybe you're trying to use the wrong field? Total slack has a specific use and is tied to the use of either deadlines or the last date in the plan. Maybe if you use the finish variance against one of the 11 baselines this will give you what you need; set up the schedule the way you want it to be, save a baseline (maybe baseline10) and then when the schedule changes you can use the finish variance against baseline10 to get the number you want?