Forum Discussion
Clemay300
Jan 18, 2024Copper Contributor
"Finish" Value in Project Center
Hello Comrades, I was hoping that one of you may be able to help me clarify what value a field is displaying in the Project Online (PWA) Project Center. The field in question is the "Finish" fie...
- Jan 19, 2024Yes, those two assumptions would be true. And you are more than welcome for the help, my friend!
Jan 19, 2024
Clemay300 --
The Project Center displays the Start and Finish values for the Project Summary Task (Row 0 or Task 0) in your enterprise projects. Hope this helps.
The Project Center displays the Start and Finish values for the Project Summary Task (Row 0 or Task 0) in your enterprise projects. Hope this helps.
Clemay300
Jan 19, 2024Copper Contributor
Okay awesome! Thank you. So, what I was calling the "Top-Level" task would be the Project Summary Task.
Would the following be true then?
Project Summary Task Start = ProjectLateStart
Project Summary Task Finish = ProjectLateFinish
Thanks again!
- Jan 19, 2024Yes, those two assumptions would be true. And you are more than welcome for the help, my friend!