Forum Discussion
Nicolas_JOURJON
Jun 30, 2023Copper Contributor
Find out the remaining work on a linked task in another file
Hello, I have a problem when I link tasks on two different files on MS Project. I have a file A with tasks 1, 2 and 3 and a file B with the link on tasks 1, 2 and 3 of file A. The start dates a...
- Jul 07, 2023Nicolas,
I'm sorry you are having difficulty trying to decode my address. Take another look at what I provided, there is no "john.project". If and when you figure it out do NOT post it to this, or any other, forum.
John
John
Nicolas_JOURJON
Jul 05, 2023Copper Contributor
Hello again,
We use a "Ressource file" but I think that it doesn't matter for the job.
I begin to do VBA, and it's not a total mess.
I have some difficulty to erase the wrong "remaining work" on RTP file... and to replace it.
thanks,
Nicolas.
Juste for my curiosity, where you come from?
We use a "Ressource file" but I think that it doesn't matter for the job.
I begin to do VBA, and it's not a total mess.
I have some difficulty to erase the wrong "remaining work" on RTP file... and to replace it.
thanks,
Nicolas.
Juste for my curiosity, where you come from?
John-project
Jul 05, 2023Silver Contributor
Nicloas,
I got a little "break in the action" so I'll give a quick reply.
You're right, having a resource pool file shouldn't impact what you are trying to do but many times a user poses a question without giving us full "disclosure" on their file structure and often it can make a big difference on how we respond.
You might want to try contacting me directly again now that I explained how to un-encode my address. If you need help with your macro code I'll need to see what you have.
For reference I'm in the United States. I assume you are in France so we have about a 9 hour difference and yes, that does mean a limited window for communication.
John
I got a little "break in the action" so I'll give a quick reply.
You're right, having a resource pool file shouldn't impact what you are trying to do but many times a user poses a question without giving us full "disclosure" on their file structure and often it can make a big difference on how we respond.
You might want to try contacting me directly again now that I explained how to un-encode my address. If you need help with your macro code I'll need to see what you have.
For reference I'm in the United States. I assume you are in France so we have about a 9 hour difference and yes, that does mean a limited window for communication.
John
- Nicolas_JOURJONJul 07, 2023Copper ContributorHello again,
I realy don't find your email adress.... I try more than 20 times !
With .icoud.com and the begining that I undertand... (not well I think)
I will go to weekend and I'll try monday, maybee the weekend is good to think.
Nicolas - John-projectJul 07, 2023Silver ContributorNicolas,
I'm sorry you are having difficulty trying to decode my address. Take another look at what I provided, there is no "john.project". If and when you figure it out do NOT post it to this, or any other, forum.
John
John - Nicolas_JOURJONJul 07, 2023Copper Contributor
On of the email address I test is the one that you can find enclose.
To be frank, the weekend I will profit of the good weather and shouldn't work.
I'll continue monday I think. And try on my side but no so easy...
Nicolas
- John-projectJul 07, 2023Silver ContributorNicolas,
I did not receive an e-mail from you. Compare my encoded e-mail to a normal e-mail address, that should help you figure out what my address is.
I'm tied up today but I will likely have time to look at your stuff this weekend. Will you be available?
John - Nicolas_JOURJONJul 07, 2023Copper Contributor
- Nicolas_JOURJONJul 07, 2023Copper ContributorJohn,
I send you an email and I didn't Know if you recieved it. (Maybe a mistake in your email adress).
I would like to have a VBA programme that put a 0 in the data "Work" on the RTP file on MS project. And then put the RemaingingWork of the Master file in the same line on the RTP file.
The tasks concerned are the tasks with the field "Code task" fill with "Valid". See the picture enclose.
Thanks,
Nicolas