Fill in Project Start Date

What magic do I need to series fill a date? Like in Excel. I had to do manually.

For example:

Start
Mon 10/11/21
Tue 10/12/21
Wed 10/13/21
Thu 10/14/21
Fri 10/15/21

 

Wayne

6 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    WayneDoubleu 

    Sorry but Project does not have that feature. It could be done with a little VBA but that's it.

    John

      • John-project's avatar
        John-project
        Silver Contributor
        Wayne,
        You're welcome and thanks for the feedback.
        I think the feature is appropriate in Excel because users are often creating spreadsheets with a consecutive dates, (I do that myself), but there are very few instances in a schedule where the dates are consecutive.
        John