FILE TASK DATES CHANGE UPON OPENING FILE
Hello All. Need a fix for Project file issue. and Individual emailed out a Project file to several of us. However, when I open the file some of the dates change from 2023 to 2025 and 2026. I asked...
John-project
May 11, 2023Silver Contributor
willard800,
Take a look at your option settings for Project. Do you perhaps have your option set to use a non-default fiscal year for all new projects (e.g. July instead of January)? Or, do you have your option set for all auto scheduled tasks to start on the current date for all new projects?
John
Take a look at your option settings for Project. Do you perhaps have your option set to use a non-default fiscal year for all new projects (e.g. July instead of January)? Or, do you have your option set for all auto scheduled tasks to start on the current date for all new projects?
John
- willard800May 11, 2023Copper ContributorThanks for your reply John. No to both. Default Fiscal Yr start January. 2) New projects - New tasks = Manually Scheduled
- John-projectMay 11, 2023Silver Contributorwillard800,
Are all the tasks in the project that was sent to you manually scheduled? What happens if you change them to auto-scheduled?
Try changing your options so that scheduling applies to the project in question instead of for "new projects".
John- willard800May 11, 2023Copper Contributorall tasks are Auto Scheduled. all are ASAP with one must start on. I changed the one constraint to ASAP, didn't change anything
"Schedule Option for this project" IS set to the File name (not New projects)