Forum Discussion
Yann-78
Dec 06, 2022Copper Contributor
external projects interdependencies on restricted access files
I would like to create cross dependencies on different project files that have restricted write access. scenario: let's say File A can be edited only by person A, but other people can read. li...
Dec 07, 2022
Yann-78 --
In a situation like this, you need someone who has permission to open and edit BOTH projects. Let's say that individual is Person C who works in the PMO. Person C should open both projects, set the cross-project dependency, then save and close both projects. Hope this helps.
In a situation like this, you need someone who has permission to open and edit BOTH projects. Let's say that individual is Person C who works in the PMO. Person C should open both projects, set the cross-project dependency, then save and close both projects. Hope this helps.
Yann-78
Dec 07, 2022Copper Contributor
thanks for your feed back. I have thought about that but it will not solve the issue of close files. I was wondering if I limited write restrictions and enforced check-in check-out would help.