Exporting resources to excel to create histogram

Hi I'm a scheduler who normally uses P6 (although I have used MS Project a little in the past!)   I'm working on a tender schedule which has a stipulation to be presented in MS Project... all good ...
  • John-project's avatar
    Jul 17, 2025

    Chris_Mercer,

    Wow, three duplicate postings, and three separate replies. My colleagues suggest a "simple" copy and paste of the Project Resource Usage data into an Excel Workbook and that will work fine, it just takes a few steps. I'm more about automation, particularly if you need to do the export on a regular basis.

    You say "Budget Work Units" but I don't think that is really what you mean. The Budget Work field is only applicable to the Project Summary Task and the file you posted to OneDrive has no Budget Work.

    As I mentioned, I have a few macros that export Project timescaled data to Excel. One in particular is very close to what you need. As currently configured, it produces three Work fields for each resource, but that is easy to reconfigure. Here is sample outut of the macro run on your file. If you are interested in an automated approach, let me know.

    John