Export a project as .mpp from Project Online
Hi, I have a project created in Project Online and need to share the .mpp project file with a client. However, although there are options to export as Excel or PDF, I am unable to export to .mpp. Is ...
Henri_3439
Feb 12, 2025Brass Contributor
Hi Dale, thanks for your quick reply!
Ok, this is not possible and still not on the table of Microsoft to add this feature.
Then I suggest another workaround: is it possible to use the new Planner and share that with an external customer and to set it that only he can view and not edit?
bwpgmr83
Feb 20, 2025Copper Contributor
Yes you can bring them in as a guest which is automatically read-only or create an account for them and only give it read-only access.