Forum Discussion
Meghanath1675
Jun 30, 2022Copper Contributor
Export a project as .mpp from Project Online
Hi, I have a project created in Project Online and need to share the .mpp project file with a client. However, although there are options to export as Excel or PDF, I am unable to export to .mpp. Is ...
Paul_Mather
Jul 01, 2022MVP
Hello Meghanath1675 ,
As you have found you will need to use Microsoft Project Desktop on a Windows device to save out a project as an .mpp file. The URL to use will be use PWA homepage URL but remove the /default.aspx from the end.
Paul
StephanGee
Aug 24, 2022Steel Contributor
But if there is no PWA Website existing? You can also create Project on the Webs by just get the user a project license.
I have the same problem - 4 year - 850 days project. If i try to export from "the web" as PDF it is just garbage. If i try to export it to excel and import to Project Client - it has a different structure (why!! btw).
How can i easy switch back to Project Client to share "good looking" PDFs with my client?
BR
Stephan