AlexTramac
May 24, 2023Copper Contributor
Exclude a person in the leveling
Hi all, I would like to know if it is possible to exclude a resource from leveling in Microsoft Project 2021. I have a supervisor who takes care of sending the parts to suppliers who will work on t...
AlexTramac
May 24, 2023Copper Contributor
Hi John,
Everything looks to be leveled for everyone. If I want to take out only 1 person from the level, can I do it and if "yes", how?
Everything looks to be leveled for everyone. If I want to take out only 1 person from the level, can I do it and if "yes", how?
John-project
May 24, 2023Silver Contributor
AlexTramac,
The easiest way to remove a specific resource from the leveling operation is to set the task or resource assignment priority to 1000. That essentially says, "don't level this assignment". Here's more information on that:
https://support.microsoft.com/en-us/office/priority-fields-096ac288-1507-431f-bc6f-5b8b3a6f2673
John
The easiest way to remove a specific resource from the leveling operation is to set the task or resource assignment priority to 1000. That essentially says, "don't level this assignment". Here's more information on that:
https://support.microsoft.com/en-us/office/priority-fields-096ac288-1507-431f-bc6f-5b8b3a6f2673
John