Exclude a person in the leveling
Hi all, I would like to know if it is possible to exclude a resource from leveling in Microsoft Project 2021. I have a supervisor who takes care of sending the parts to suppliers who will work on t...
John-project
May 24, 2023Silver Contributor
Yes you can keep tasks for one or more resources from being leveled. Assuming you are using the stand alone desktop version of Project, you should see these options:
Hope this helps
John