Exceptions for Resource Group Calendar?

What is the best way to track vacations and time off for a resource group? Is there a way to place exceptions in the resource group calendar or does this necessitate having individual calendars for t...
  • John-project's avatar
    John-project
    Feb 20, 2023
    Mark_D_Hill,
    Yes you can do that but remember, when that one individual is off, the max units for the group is 300%. In that regard, the group "days off" should be handled by the Resource Availability as opposed to using Exceptions. An exception would apply to the whole group, unless perhaps all members of the group have a common time off, like for training or something.

    You may find its easier to work with 4 individual resources than trying to use a group resource, particularly with discretionary days off.

    I suggest you try a couple scenarios doing it each way (i.e. group versus individual) and see if either is a clear winner for what you need.

    John