EVM with project- taking into account "cost" resource
I need the forum help. what is the best way to take "cost" resource into the EVM calculation? Once allocating cost to an activity, it does take it into the BCWS- the total cost of the activity. Ye...
AviShenkar
Nov 10, 2024Copper Contributor
Tnx John as to this interesting POV. Yet, I think the EV regards a certain activity or a summary task. The evaluation of the EV takes into consideration also materials and money that are introduced into this effort, so why it shouldn't be considered here as well?
John-project
Nov 11, 2024Silver Contributor
AviShenkar,
Sorry but I don't understand what you are saying. I'm simply offering a potential reason why Project's earned value metrics do not encompass the full scope of cost (e.g. real but non-earned). I suggest you submit a request through the Project portal at:
https://feedbackportal.microsoft.com/feedback/forum/40792262-301c-ec11-b6e7-0022481f8472
John