EVM with project- taking into account "cost" resource
I need the forum help. what is the best way to take "cost" resource into the EVM calculation? Once allocating cost to an activity, it does take it into the BCWS- the total cost of the activity. Ye...
John-project
Nov 10, 2024Silver Contributor
AviShenkar,
Consider this, the basic concept of earned value is to, well, earn value. Material and cost resources do not earn value, only work resources can "earn" value. Perhaps that is why the Project developers elected to not include cost and material resources in earned values metrics.