Error GeneralQueueJobFailed (26000) - UpdateSRA.UpdateSRAMessage when publishing a project
Hello, For several days now we have been receiving errors when publishing a project, errors that can be found in the configuration part of project online (queue management). An example of an error i...
TonyProctor
Dec 17, 2022Brass Contributor
A couple things to check on this:
1. Open the schedule and verify there are NO blank lines in your schedule
2. Verify that all of the enterprise resources STILL exist in your enterprise resources
3. No assignments to summary tasks
4. Look at your default Gantt chart view and fix any start/finish dates with the red squiggly lines.
If all of those are good and still have errors, let us know and we can go down the list of other culprits.
1. Open the schedule and verify there are NO blank lines in your schedule
2. Verify that all of the enterprise resources STILL exist in your enterprise resources
3. No assignments to summary tasks
4. Look at your default Gantt chart view and fix any start/finish dates with the red squiggly lines.
If all of those are good and still have errors, let us know and we can go down the list of other culprits.