Enterprise Custom Fields Project For the Web & How to report off custom fields

What are the options for having a custom enterprise field on the project task level?  I would like each project task to have a field called "Charge Code".   When you add a custom field it says that...
  • Paul_Mather's avatar
    Mar 26, 2024

    Hello psawyer ,

    Unfortunately this is a limitation in Project for the web, task level custom fields you add to a project are only local to that project and the fields are not available for reporting etc.

    Paul