Forum Discussion
psawyer
Mar 25, 2024Iron Contributor
Enterprise Custom Fields Project For the Web & How to report off custom fields
What are the options for having a custom enterprise field on the project task level? I would like each project task to have a field called "Charge Code". When you add a custom field it says that...
- Mar 26, 2024
Hello psawyer ,
Unfortunately this is a limitation in Project for the web, task level custom fields you add to a project are only local to that project and the fields are not available for reporting etc.
Paul
Paul_Mather
Mar 26, 2024MVP
Hello psawyer ,
Unfortunately this is a limitation in Project for the web, task level custom fields you add to a project are only local to that project and the fields are not available for reporting etc.
Paul