End dates of Subtask are appearing wrong

Hi there, I'm facing issue with import of xml file. When I import the file, Finish date of task having subtask, gets disturb. I am attaching the screenshot from xml file indicating the dates that I ...
  • Ignacio_Martin's avatar
    Feb 04, 2025

    Hello again Saleem

    If you want the summary task to be independent of the subtasks it groups, you must include the following instructions in the corresponding summary task of the xml schema you want to import:

    <ManualStart>2024-12-26T00:00:00</ManualStart>
    <ManualFinish>2024-12-29T23:59:00</ManualFinish>
    <Manual>1</Manual>

    The order and place in which they are within the task does not matter, even if there are <Start>... and <Finish>... instructions, because when defining the task as Manual, only manual dates will be considered.

    You must write the instructions exactly as shown above, respecting upper and lower case.

    You must also write the end date as: 2024-12-29T23:59:00 and not as: 2024-12-29T23:59:59, in which case it will skip to the next day and count one more day when importing the schema file.

    Going back to your initial request, it would look like this:

    <Name>Testing</Name>
    <Type>0</Type>
    <IsNull>0</IsNull>
    <WBS>3</WBS>
    <OutlineNumber>3</OutlineNumber>
    <OutlineLevel>1</OutlineLevel>
    <Priority>500</Priority>
    <ManualStart>2024-12-26T00:00:00</ManualStart>
    <ManualFinish>2024-12-29T23:59:00</ManualFinish>
    <Manual>1</Manual>

    If you consider that it has been useful and sufficient, you can close the query by clicking Solved.

    Ignacio