Effort and Workload on Joint Tasks

Please can someone help us with the following scenario? 😊   Task A is scheduled next week, 8th to 12th May 2024, and has two resources assigned to it (Resource 1 & Resource 2) and the effort to co...
  • Dale_HowardMVP's avatar
    Apr 05, 2024
    SPQR1965 --

    The PM needed to enter the Actual Work for the resource assignment and not for the task. To do this, he/she should have applied the Task Usage view and then applied the Work table. In the Work table, he/she would be able to enter 1h in the Actual Work field for Resource 1. Hope this helps.