Effort and Workload on Joint Tasks
Please can someone help us with the following scenario? 😊 Task A is scheduled next week, 8th to 12th May 2024, and has two resources assigned to it (Resource 1 & Resource 2) and the effort to co...
- Apr 05, 2024SPQR1965 --
The PM needed to enter the Actual Work for the resource assignment and not for the task. To do this, he/she should have applied the Task Usage view and then applied the Work table. In the Work table, he/she would be able to enter 1h in the Actual Work field for Resource 1. Hope this helps.
SPQR1965
Copper Contributor
Dale_HowardMVP We have tried that. Inserting 1.05 hours as shown below. However, when we save and change the view to a Gannt it has not picked up upon the 1.05 hours. Any ideas please? Thank you.
Apr 05, 2024
SPQR1965 --
Did you change the Actual Work to 0h on the task in the Gantt Chart view before you entered the 1h for the resource assignment in the Task Usage view? I should have mentioned that would be the preliminary step before entering the Actual Work in the Task Usage view
Did you change the Actual Work to 0h on the task in the Gantt Chart view before you entered the 1h for the resource assignment in the Task Usage view? I should have mentioned that would be the preliminary step before entering the Actual Work in the Task Usage view