Forum Discussion

dpconsult2025's avatar
dpconsult2025
Copper Contributor
Nov 08, 2021
Solved

Duration1, Duration2, Duration3 used to calculate project costs from Resource Sheet

I am seeking advice as to how I can calculate resource costs from Duration 1, Duration2 Duration3, etc, and ignore Duration which all costs are currently calculated from.    Duration1, 2 & 3 are ef...
  • John-project's avatar
    John-project
    Nov 10, 2021

    dpconsult2025 

    I assume the work effort, which is normally expressed in hours, is 40 hours (5 days) for Vendor 1 and 100 hours (12.5 days) for Vendor 2.

     

    The screen shot shows custom fields for TM effort, Change Mgmt effort and DXC effort which I also may assume are the Duration1, Duration2, and Duration3 fields. Extra fields (e.g. Duration1, etc.) are static fields, they have no relationship to Project's scheduling or costing calculations. You have assigned resource DXC to the task and if you are getting a task cost of $408 then you apparently have assigned DXC, whose standard rate is $1/hr, at 100%. Project will therefore linearly spread that assignment over the full 51 days of task duration.

     

    Here's what you need to do. Forget the custom Duration fields to entering/tracking vendor effort.

    1. Create three resources on the Resource Sheet, Vendor 1, Vendor 2, Vendor 3, each with an hourly rate of $1/hr.

    2. Create a Fixed Duration type task of 51 days.

    3. Assign Vendor 1 and Vendor 2 at 100%. That will initially give the following result

    4. Switch to the Task Usage view. Edit the Work hours for each resource assignment as shown. Note Project will automatically linearly spread each resource's hours over the full 51 day task duration. If you want the spread to be different, manually edit the timescale data (right side of view) as needed.

    Does that give you what you need?

     

    Many times when an external supplier (e.g. contract, vendor, etc.) is needed for a plan, that supplier has a fixed price contract to do whatever work is required. Is that better describes your scenario, then that cost is handled differently.

     

    John