Duration decreases when asign more than one work resource
I have a problem with project, when asign more than one work resource to a fixed units task, the duration is decreased by project. It did not happen before. It reduce duration! it ...
Ignacio_Martin
May 06, 2024Steel Contributor
Hola Luis
The Type of task that maintains the Duration of the task when increasing its number of resources is Fixed Duration (Duración fija).
The Fixed Units (Unidades fijas) task type is used to maintain the number of Resource Units assigned to the task when the user changes the Duration of the task or the amount of Work of the resources in the task.
Ignacio
The Type of task that maintains the Duration of the task when increasing its number of resources is Fixed Duration (Duración fija).
The Fixed Units (Unidades fijas) task type is used to maintain the number of Resource Units assigned to the task when the user changes the Duration of the task or the amount of Work of the resources in the task.
Ignacio