Forum Discussion
sovan_ban
Jul 08, 2021Copper Contributor
Does the 'Check in' activity for a project in Project online instance create Queue Jobs
Does the 'Check in' activity for a project in Project online instance create Queue Jobs
- Jul 08, 2021sovan_ban -- Yes, the Check In action creates a Check in job in the Queue. Hope this helps.
Kelvin_Kirby
Jul 09, 2021Iron Contributor
Yes it does. Moreover you can use PowerAutomate to set up an automated notification of the check-in should you wish to do so. There are also some utilities that will force check-in project plans for you if necessary. Just be aware that when you force check-in a project, any changes made to the plan since the last save will be lost. And as a best practice, users should always close and check-in projects when they have finished working on them. Hope that helps! 🙂