Do we have any work-around for Subproject in P4W
Hello All With construction projects, there are many sub-projects involved, but P4W does not support Sub-projects. Is there any work-around solution for the need to manage sub-projects? Thank...
- Apr 24, 2024daibt --
If you need to be able to create master projects, then Project Operations and Project for the Web are absolutely the WRONG tools for you to use. If you need enterprise capabilities, along with master projects, you should be using Microsoft Project with either Project Online or Project Server. Hope this helps.
malshayeb
Apr 22, 2024Brass Contributor
Hi Daibt,
I agree with Dale, you should be using a different tool, Project for web is not there yet. and i assume you want to create task dependencies across projects ..etc, i would recommend you look around in the Microsoft partners solutions
I agree with Dale, you should be using a different tool, Project for web is not there yet. and i assume you want to create task dependencies across projects ..etc, i would recommend you look around in the Microsoft partners solutions