Do we have any work-around for Subproject in P4W
Hello All With construction projects, there are many sub-projects involved, but P4W does not support Sub-projects. Is there any work-around solution for the need to manage sub-projects? Thank...
- Apr 24, 2024daibt --
If you need to be able to create master projects, then Project Operations and Project for the Web are absolutely the WRONG tools for you to use. If you need enterprise capabilities, along with master projects, you should be using Microsoft Project with either Project Online or Project Server. Hope this helps.
KimaniT
Apr 21, 2024Copper Contributor
Well...there is a semi way of doing what you are looking for...IF I understand your problem. You can make your "MasterPproject" your overall program, and those "Sub projects" you mentioned into regular projects regular projects within your program. This is a trick in Project Desktop...but in P4W ist called a "Roadmap"
Hope that helps!