Display resource name in timeline

Hi,

I have a nice timeline with my milestones, but I can't seem to find a way to simply display the resource next to the milestone (in the timeline!)

  • brentrug

    You mention wanting a resource shown next to a milestone. For reference, milestones are not tasks, they are simply a point in time (i.e. 0 duration). As such, milestones should not have any resources assigned except perhaps a cost if the milestone is representing payment or receipt thereof.

     

    But to answer your question, unfortunately the only way to show a resource next to a task bar (or milestone) on the Timeline is to include that resource as part of the task name.

     

    John

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor

    brentrug

    You mention wanting a resource shown next to a milestone. For reference, milestones are not tasks, they are simply a point in time (i.e. 0 duration). As such, milestones should not have any resources assigned except perhaps a cost if the milestone is representing payment or receipt thereof.

     

    But to answer your question, unfortunately the only way to show a resource next to a task bar (or milestone) on the Timeline is to include that resource as part of the task name.

     

    John