Display Auto-Populated Resource Field on Task Sheet

I have a list of resources and associated info (resource name, group, etc...). Two of these fields are customer resource fields (Text1, Text2). When I am on my Task Sheet I select a resource and the Resource Group field auto-populates. However, I need those other fields from the Resource list in my view as well, and when I try to add them, it only allows me to select Task fields (i.e. not all resource fields are in the list). Is there any way to do this?

  • John-project's avatar
    John-project
    May 19, 2021

    The macros in the Wiki article are structured to transfer assignment data to task data or vice versa. It sounds like like what you want to do is to transfer resource data to task data. That is easy enough as long as there is only one assigned resource per task but it presents a dilemma if more than one resource is assigned to a given task, as is often the case.

    However, if you do have a single resource assigned to each task, then this code should give you what you want.
    Sub ResToTsk()
    Dim t As Task
    For Each t In ActiveProject.Tasks
      If Not t Is Nothing Then
        If t.Assignments.Count > 0 Then
          t.Text1 = ActiveProject.Resources(t.Assignments(1).ResourceID).Text1
          t.Text2 = ActiveProject.Resources(t.Assignments(1).ResourceID).Text2
        End If
      End If
    Next t
    End Sub

    If you have more than one resource assigned per task, then you need to determine which resource's custom field is transferred to the task custom field.
    John

8 Replies

    • AndrewButters's avatar
      AndrewButters
      Copper Contributor
      I got the macro to work but only see the change on the Task Usage View but what I really need is for it to show up when I'm editing from the Task Sheet. I tried removing and re-adding the fields to the Task Sheet but the data only shows up when I am looking at the Task Usage View. Any thoughts?
      • John-project's avatar
        John-project
        Silver Contributor

        The macros in the Wiki article are structured to transfer assignment data to task data or vice versa. It sounds like like what you want to do is to transfer resource data to task data. That is easy enough as long as there is only one assigned resource per task but it presents a dilemma if more than one resource is assigned to a given task, as is often the case.

        However, if you do have a single resource assigned to each task, then this code should give you what you want.
        Sub ResToTsk()
        Dim t As Task
        For Each t In ActiveProject.Tasks
          If Not t Is Nothing Then
            If t.Assignments.Count > 0 Then
              t.Text1 = ActiveProject.Resources(t.Assignments(1).ResourceID).Text1
              t.Text2 = ActiveProject.Resources(t.Assignments(1).ResourceID).Text2
            End If
          End If
        Next t
        End Sub

        If you have more than one resource assigned per task, then you need to determine which resource's custom field is transferred to the task custom field.
        John

    • AndrewButters's avatar
      AndrewButters
      Copper Contributor

      John-project Thank you, I will check out the article. I'm no stranger to VBA and really hoping to avoid manual entry since I have hundreds of these things to maintain.