Forum Discussion
ware32
May 02, 2024Copper Contributor
disallow timesheet recovery
Is it possible to configure microsoft project server 2019 on premise to NOT allow users recovery the timesheets already approved by the project leader?
May 02, 2024
ware32 --
I did some research on your problem, and there is no security setting that would allow you to block team members from recalling timesheets they have previously submitted for approval. This means you need to make this a "training and performance" issue with your team members. Sorry, but hope this helps.
I did some research on your problem, and there is no security setting that would allow you to block team members from recalling timesheets they have previously submitted for approval. This means you need to make this a "training and performance" issue with your team members. Sorry, but hope this helps.
- ware32May 02, 2024Copper Contributorwhat does it mean? (training and performance issue)
- May 03, 2024Teach people what you want them to do and then hold them accountable for that behavior.