Forum Discussion

MMF200's avatar
MMF200
Copper Contributor
Mar 13, 2024
Solved

Different "unit" calculation by version "2026" and "Project Online Desktop-Client"??

Hello community,   I have a problem between the MS-Prject Version 2016 and Project Online Desktop Client.   I have in Project 2016 follwed behavior: Start with                                  ...
  • John-project's avatar
    John-project
    Mar 13, 2024

    MMF200 

    There was a change made in the way Project shows Assignment Units but I don't recall when that happened. When a resource is initially assigned the Assignments Units field shows the assignment level. However if the work is then changed, the Assignment Units field will "lag" the new value. The new value is shown in the Peak field. For example, this is how the initial assignment appears in the Task Usage view:

    When the work is doubled, this is how it will appear:

     

    You may find this article helps explain:

    https://www.mpug.com/eliminate-the-confusion-understanding-the-peak-field

    John

Resources