Different "unit" calculation by version "2026" and "Project Online Desktop-Client"??
- Mar 13, 2024
There was a change made in the way Project shows Assignment Units but I don't recall when that happened. When a resource is initially assigned the Assignments Units field shows the assignment level. However if the work is then changed, the Assignment Units field will "lag" the new value. The new value is shown in the Peak field. For example, this is how the initial assignment appears in the Task Usage view:
When the work is doubled, this is how it will appear:
You may find this article helps explain:
https://www.mpug.com/eliminate-the-confusion-understanding-the-peak-field
John
Hi MMF200
Since a previous version that I don't remember, Project shows as Resource Units the initial value or the one entered manually in the forms. It is a criterion that I believe has its share of logic, since this percentage of unit allocation can vary depending on the day of the task, and you have to choose a value to display in a single cell.
Actually, Project does calculate the Percent allocation of the fixed duration task when changing the Work, but to see it you have to go to the Task Usage view, or Resource Usage, and select the Percent allocation field in the time phase on the right .
Note that the unique value of the Peak column in the assignment table is the maximum percentage or number of units for which a resource is working at any time on the assignment.
By the way, the fact that an overallocated resource icon is displayed in the indicators column of this example confirms and assumes that Project is assigning two Arbeiter A resources, when in this example only one exists in the project.
I hope I've helped.
Ignacio