Detailed question about comparison of 2 Microsoft Project files
Hi there, I'm very clear on how to perform a comparison of two Microsoft Project files which share an ancestry (e.g. you've created a project, some changes occur over a month, and then you compar...
John-project
May 22, 2024Silver Contributor
Gilbert,
What exactly is the add-in you are trying to use? I suggest you contact whoever created the add-in to find out how it's supposed to work.
The Compare Projects utility found under, Report > Project group > Compare Projects is not an add-in, it is included as part of the Project app.
John
What exactly is the add-in you are trying to use? I suggest you contact whoever created the add-in to find out how it's supposed to work.
The Compare Projects utility found under, Report > Project group > Compare Projects is not an add-in, it is included as part of the Project app.
John
bertwong1
May 22, 2024Copper Contributor
I also created that add-in, I am using VB.net. Initially, the add-in performs different reports. Now, I was instructed to create something similar to Compare Projects.
- John-projectMay 22, 2024Silver Contributor
bertwong1,
So. . . . why not use the Compare Projects utility? I created my "wheel" way back when because it didn't exist, so writing my own compare macro made sense. But now that the built-in utility exists, why "re-invent the wheel"?
John