Desktop Project will not Import to Project Online
Hello, I am having an issue where some of my desktop projects are not importing to Project Online. Some files imported without issues, but others will not. I saw an earlier post about this but...
sshaffery
Oct 12, 2022Copper Contributor
I think I figured out my issue so I am posting incase someone else has the same problem. The files that would not load all had Baselines built in. I exported just the task data out to excel, reimported into project without the baseline. Now the file loads into Project Online without issue.
John-project
Oct 12, 2022Silver Contributor
sshaffery,
Okay, I'm glad you found a solution.
John
Okay, I'm glad you found a solution.