Dependency Options
Hi community,
I recently started using MS Project Web version and it is so pared down compared to the desktop program. I am looking for dependency options like Finish>Start (FS), Start>Finish (SF), Start>Start, (SS) Finish>Finish (FF) and I fear it doesn't exist.
Please help!
Thanks very much
2 Replies
Sort By
- CC_GV --
Project for the Web currently offers only Finish-to-Start dependencies. However, in the future, Microsoft intends to expand this to include the other three dependency types you list. Refer to the following to see the roadmap of new features planned in the future:
https://techcommunity.microsoft.com/t5/project-blog/september-update-blog/ba-p/2803540
Hope this helps.- CC_GVCopper Contributor
Can't wait, thanks! Dale_HowardMVP