Forum Discussion
momentumbrian
Aug 02, 2023Copper Contributor
Dependencies on Cloud Based Project
Im using the cloud based version of MS PROJECT. I’m running into a glitch on simply connecting dependencies. I could connect dependencies at one point but now they show up and I cannot choose them. A...
Aug 03, 2023
momentumbrian --
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
M_Altobelli
Aug 04, 2023Tin Contributor
Tested, I can set simple FS dependencies using the right-click method successfully, but when I try to set via the timeline, they don't stick and the lines disappear when I move to another tab (e.g. Boards) and back.