Dependencies on Cloud Based Project
Im using the cloud based version of MS PROJECT. I’m running into a glitch on simply connecting dependencies. I could connect dependencies at one point but now they show up and I cannot choose them. A...
Aug 03, 2023
momentumbrian --
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
Select a block of tasks that you want to link, right-click anywhere in the selected block, and then select the Add Dependency item on the shortcut menu. Does that work for you? I just tested and it does work for me. Let us know and we will try to help you.
- momentumbrian2325Aug 04, 2023Copper Contributor
Dale_HowardMVP This did work for me. Hoping it goes back to the intended format via the timeline or dependency column or even via the "open details" prompt. Thank you!
- mattsears1818Aug 04, 2023Copper ContributorThanks, Dale. This works for me. It's an extremely slow process compared to how I normally do it... but it does work for now.
- M_AltobelliAug 04, 2023Tin ContributorTested, I can set simple FS dependencies using the right-click method successfully, but when I try to set via the timeline, they don't stick and the lines disappear when I move to another tab (e.g. Boards) and back.
- momentumbrianAug 03, 2023Copper ContributorHi dale. Thank you for the reply. I’ll try this when I get to the office tomorrow. Just curious, are the other options to create a dependency also blocked for you? One being the dependency column and simply typing the associated dependency line in that block to link i? Or the highly suggested one, in the timeline screen, simply dragging the dot to the wanted dependency? None of these work for me. NOTE: I’m working on the web version.