Forum Discussion

Oliver_complean's avatar
Oliver_complean
Copper Contributor
Sep 26, 2020
Solved

Dependencies between subprojects possible?

Dear All,   I have three subprojects (A, B and C) which I combine in one main project. I added the subprojects using "Insert subproject". They show up as expected, but it seems that I cannot set d...
  • Ade_Budiman_Lim's avatar
    Oct 09, 2020

    Oliver_complean From my understanding, you want to link Task from sub Project A and Task from sub Project B? Yes you can do that in Ms Project. Just select the two Task you want to be linked then click the Link icon. Please see my attachment as example.