Decimal places of MS project custom field

i, Hi, I am new to MS project, I am preparing the project report with the planned percentage of completion. Since this column has the formula to convert number into percentage, it is giving lon...
  • John-project's avatar
    John-project
    Jun 14, 2022

    Jhonex1 

    Use this construct for the custom Text4 field:

    Text4=format([Number3],"##.#") & " %"

    John