"Deadlines" to start by
Deadlines are useful, since they do not shift when the project is recalculated. Is there a way to set a "deadline" that indicates - "must start by", instead of "must be completed by"? (I guess I co...
Paul_Mather
Mar 13, 2023MVP
Hello Yaakov_Shaked ,
You can use a new custom Start field and add that to the Gantt - rename the field as needed:
Right click on the Gantt then click Bar Styles and add the new bar style, example below:
Hope that helps
Paul